4. Export: divide the product into rolls (or cut into single sheets according to the required size)

1. Uncoiler: Its main task is to stably convey the uncoiled substrate according to the frequency conversion working frequency.
2. Stitching machine: It is mainly used to sew the joints of the strip to ensure stable production.
3. Tension machine: It is an effective tension and tension system. The tension is generated by the speed difference of the production line. The function is to ensure the smooth running of the steel plate and avoid scratches on the steel plate without supporting the furnace bottom. The magnitude of the tension directly affects the harvest Volume quality.
4. Uncoiling looper: The function of the uncoiling looper ensures the continuation of the production of the strip, because the rich strip of the looper guarantees the effective and sufficient production time for the strip when connecting the strip.
5. Alkaline degreasing: It cleans the oil stains and impurities of the substrate to ensure the cleanliness of the board surface, which is the basis for the later process of painting.
6. Cleaning: After degreasing, the remaining liquid on the board must be cleaned with clean water to ensure that there is no remaining liquid, so as to prepare for the later work of product quality.
7. Drying: After cleaning, there is a drying oven to prepare for the first coating.
8. Initial coating: The initial coating process of primer and back paint is completed at this site.
9. Drying: After the initial coating is completed, enter the drying oven to complete the curing and drying process. The temperature and speed of this step is very important, and it is ready for the next top coat fine coating.
10. Finish coating: This site is the last stop for finishing the main color of the color steel plate topcoat. The tasks are completed according to customer requirements and production requirements.
11. Drying: After finishing the top coat, enter the drying furnace to complete the main process part of the product.
12. Air-cooled cooling: Since the product has a high temperature when it comes out of the drying oven, in order to reach the winding temperature, air cooling or water cooling must be performed at the same time, and the winding temperature should not exceed 40℃.
13. Winding looper: The main function is to ensure the effective time of the unwinding work of the winder.
14. Winding machine: According to the winding signal of the electronic probe, the steel coil can be wound evenly on the edge to meet the quality requirements of the industry.